Change order template

A change order is a signed record that changes a job's scope, price or schedule after the estimate was accepted. It lists the change, the cost added or credited, the new total and the new completion date.

Word (.docx)

A filled-in example

Change order #3 to Estimate #1042. Adds $640 and 1 working day. Revised contract total: $15,140.

Bayview Tile and Bath

office.bayview@example.com · (555) 010-4127

Change order

CO-3

Prepared for

Carmen Ruiz

Valid until

October 20, 2026

Estimate total

$640.00

DescriptionQtyAmount
CO #3: Recessed shower niche, framing and waterproofing1$380.00
CO #3: Tile for niche, labor and materials1$260.00
Total
$640.00

Change order #3 to Estimate #1042. Adds $640 and 1 working day. Revised contract total: $15,140.

Example change order with sample prices.

What does a change order include?

A change order should stand on its own, so anyone reading it later can see what changed and who agreed. Number each one and tie it to the original estimate or contract.

Both sides should sign and date it. A signature, or a written approval such as an online acceptance or an email reply that names the change order, shows the client agreed to the new price before the work was done. Some states require changes to home improvement contracts to be in writing and signed, so check your state's rules.

FieldWhat to writeExample
Change order numberA sequential number for the projectCO #3
Original estimate or contractThe number and date of the accepted priceEstimate #1042, accepted March 3
Description of changeWhat is added, removed or substituted, and whyAdd recessed tile niche in shower wall at owner's request
Price changeLabor and materials for the change, as an add or a creditAdd $640
Revised contract totalOriginal total plus all approved changes$15,140
Schedule impactDays added, or no changeAdds 1 working day
ApprovalNames, signatures and dates for both sidesOwner and contractor, March 21

When should I use a change order?

Use one any time the work or the price moves away from what the client accepted. That includes client requests, hidden conditions you find after opening walls, material substitutions and allowance overages.

Write it before you do the extra work, not after. A change order signed after the fact is better than nothing, but a client is more likely to dispute a charge they first hear about on the invoice. Even a small change, such as moving an outlet, is worth a one-line change order on a busy job.

How do I price a change order?

Price it the way you priced the original estimate: labor hours at your rate, materials at cost plus your usual markup, and any added equipment, disposal or permit costs. Include overhead and profit, since the change takes your time like any other work.

For removed work, show a credit and the lower total. If the size of the change is uncertain, such as rot repair you can't fully see yet, agree on a unit price, for example per sheet or per linear foot, and bill the actual quantity once the client approves the rate in writing.

How do I add approved changes to the invoice?

Add each approved change order to the next invoice as its own line, labeled with its number, such as 'CO #3: shower niche, approved March 21.' Keep the original estimate lines unchanged, so the client can trace the total from estimate to change orders to invoice.

In Invoicefy, convert the accepted proposal to an invoice in one click, then add each approved change as a new line before you send it. If you bill in stages, put each change on the invoice for the stage when the work was done.

Questions people ask

It should be approved in writing by the client before the work is done. A signature is best, and an email or online approval that clearly names the change order is far better than a verbal okay. Some states have specific rules for home improvement contracts, so check yours.